We partnered with John Fillmore Contracting and City Care to deliver this iconic project using our K-Form Construction Joint. By replacing conventional ‘hit and miss’ boxing with K-Form, the team was able to set up the entire area ahead of the pour and complete the concrete placement in one continuous pour.
This not only sped up construction time, but also reduced labour requirements onsite, improved pour accuracy, and created a safer, more efficient workflow for the crew. K-Form’s stay-in-place design helped streamline the project while delivering clean, consistent construction joints across the slab.
"Using the K-Form system saved us time and money, and considering the tight time constraints, was a huge contributing factor in delivering the project on time. iNFORCE's service was exemplary, ensuring product was always available and delivered on time."
Tony Munro JFC/City Care JV Concrete/Paving Manager